01 Challenge
The B&O Trail extension project aimed to enhance connectivity and recreational opportunities in Speedway and Indianapolis. The challenge was to manage the development of a 4.15-mile asphalt multi-use trail, including both eastern and western extensions to the 1.5-mile B&O Trail completed in 2018.
02 Solution
Veridus Advisors supported the project, overseeing the extension in three key phases: Preliminary Design and Land Acquisition, Design Management, and Construction Oversight. This included managing design professionals, guiding land acquisition, refining plans, and ensuring effective construction oversight.
03 Results
The project successfully extended the B&O Trail by 2.65 miles, including a new bridge over Eagle Creek and new pathways in Haughville and High School Road. Completed two months ahead of schedule in May 2023 and within the $1.7 million budget, the trail now significantly enhances community connectivity and recreational options.
Quick Facts
Size: 2.65 miles
Construction Timeline: Aug. 2021 – May 2023
Constructor: Beaty Construction
Engineer: Infrastructure Engineering
Cost: $1.7 million